Designed and constructed the WTP along with production wells and pressure boosting system.
Technologies used: Iron Removal Filters (IRF), Sediment Filter (SF), Multi Media Filter (MMF), Demineralization (DM), Chlorination and De-chlorination.
Treatment Plant, Capacity: 6.0 MGPD
Production wells, Pressure Boosting System.
Pipe lines (05 KM) up to 600 mm dia.
25 m Dia. & 11 m Depth Semi-Ground RCC Clarifier, RCC.
Equalization Tank and different types of RCC Water Treatment Structures..
7 k m effluent Collection network up to 1500 mm dia.
Raw water source: Groundwater.
Total number of industries serving: 50+.
Total number of workforce in the EPZ: 40,000+ .
WTP operating since 2010 .
30 years contract (auto renewable) with Bangladesh Export Processing Zone Authority (BEPZA) under Prime Minster Office.